Passage Planning: Appraisal, Planning, Execution, Monitoring

The four stages of passage planning required by SOLAS V/34 and IMO A.893(21): what to gather, what to put on the chart or ECDIS, how to brief and run the plan, and how to monitor it until the next berth. A core MCA oral subject: examiners want the stages in order, with real examples.

Last reviewed 1 Nov 2026 · From a professional captain's years of study notes · Organised with AI and checked against current regulations · How we write

https://shipshape.wiki/articles/passage-planning-apem/

On this page (9)

Why plan: the rules and the four stages

In short: Read compulsory nautical publications, chart correction, tides and ECDIS safety settings first: passage planning puts them all to work. Every ship that goes to sea must have a proper voyage plan, berth to berth (SOLAS V/34). The method is APEM: Appraisal → Planning → Execution → Monitoring (IMO A.893(21)).

The rules

  • SOLAS V/34 makes a properly prepared voyage plan mandatory for all ships that proceed to sea. Port State control can ask to see it (MGN 610 (M+F) Amendment 1, Annex A 41).
  • The plan must follow the IMO Guidelines for Voyage Planning, IMO A.893(21) (adopted 1999).
  • Under SOLAS V/34 the route must: take account of ships’ routeing systems; give sufficient sea room all the way; anticipate all known navigational hazards and adverse weather; and respect marine environmental protection measures.
  • SOLAS V/34-1: the Master’s discretion. Nobody (owner, charterer, company) may stop the Master from taking a decision needed for safety or the environment.
  • STCW A-VIII/2 Part 2 repeats the duty for the watchkeeping officers: plan before each voyage, berth to berth.
  • Small vessels and yachts: the plan is still required, but its depth depends on the size of vessel, its crew and the length of the voyage (MGN 610 (M+F) Amendment 1, Annex A 41.4).

Where the guidance lives

  • IMO A.893(21) — the four stages, the base of everything else.
  • MCA guidance Implementing SOLAS Chapter V (2002): Annex 24 = MCA guidance on voyage planning, Annex 25 = the IMO guidelines. Some references call it “SOLAS V Annex 23”: it is the same guidance.
  • MGN 166 (M+F) — the MCA note that reproduced the IMO guidelines for UK ships.
  • Today the MCA’s SOLAS V guidance is MGN 610 (M+F) Amendment 1 (2025).
  • ICS Bridge Procedures Guide, chapter 2 — industry best practice and checklists.

The aim and who does it

  • Aim: the safest and most economical passage berth to berth.
  • Priorities, in order: safety of life, then the ship, then the marine environment.
  • The OOW may prepare the plan (often the 2nd Officer, the navigating officer). The Master reviews and approves it, the officers sign it, and a copy stays on the bridge.
  • It is a bridge team job: use everyone’s experience, whatever their rank.
Stage Question it answers When
Appraisal Is the voyage possible and safe? Before planning
Planning Exactly how will we do it? Alongside, before sailing
Execution Are we ready to go, now? Day of departure
Monitoring Are we following the plan? Underway, until the berth

Appraisal: is the voyage possible?

In short: Gather and study all the information for the voyage, then make a risk assessment: are the risks acceptable, is the passage feasible and viable? (IMO A.893(21))

The 5 Cs of seaworthiness

Before the route, check the ship. Five words, all starting with C:

  1. Construction — is the vessel built and maintained for the sea expected? Hull integrity, watertightness, general physical state.
  2. Condition — are critical systems working? Engine, steering, rigging, electronics, safety equipment: the operational status.
  3. Crew — competent, qualified, rested and briefed? Their skills and their mental and physical state decide safe operation (see hours of rest).
  4. Cargo — properly loaded and secured, right for the voyage? On a yacht: fuel, provisions and guests.
  5. Compliance — legal and regulatory requirements met: certificates and documents in date, safety equipment, manning levels.

What to gather

  • Charts of an appropriate scale (see chart scales), corrected and relevant to the voyage; the chart catalogue to find them.
  • Nautical publications up to date, corrected by Notices to Mariners.
  • Sailing Directions (Admiralty Pilots).
  • Ocean Passages for the World, routeing charts, Mariners’ Routeing Guides and passage planning charts.
  • Tide tables and tidal stream / current atlases.
  • List of Lights and List of Radio Signals (radio aids to navigation).
  • Weather information: routeing-chart climate, forecasts and warnings (see weather information at sea).
  • Ice: the Mariner’s Handbook (NP100) for ice information.
  • The ship itself: draught, manoeuvring data, equipment status, company (SMS) requirements.

On the bridge: a high-latitude passage Svalbard → Jan Mayen → Iceland → Faroe → Shetland → Norway starts with ice limits from NP100 and the routeing chart for the month, before a single line is drawn.

Planning: the berth-to-berth plan

In short: Turn the appraisal into a detailed plan on the chart (paper or ECDIS) and in a notebook, from berth to berth. Then record it and get the Master’s approval (IMO A.893(21)).

What goes on the chart

  • The intended route, plotted leg by leg.
  • Hazards found in a risk assessment, and no-go areas shaded so nobody crosses them; then choose the waypoints.
  • A safe speed for each part of the passage (see safe speed).
  • Under-keel clearance (UKC) everywhere, allowing for squat.
  • TSS and VTS areas, with their rules and reporting points (see traffic separation schemes). Highlight VHF channel changes, for example abeam a given light.
  • Alteration points and wheel-over positions.
  • Position-fixing methods and intervals, and the marks to use (see position fixing).
  • Master-calling points and the aids to navigation expected along the route.
  • Expected traffic density.
  • Environmental protection: sensitive areas, discharge limits.

Radar in the plan: conspicuous targets and detection ranges

Radar plays a part in all four stages. The radar information you put in the plan (good targets, parallel index lines) becomes gold when another position-fixing system fails. Plan it carefully for coastal and restricted waters, restricted visibility, ice, and TSS / VTS areas.

  • Good radar targets give stable, clear, accurate echoes that match the chart: an isolated island, an island-reef, a cape, a jetty, an isolated lighthouse, cliffs with headlands, a racon. Prefer targets that are near, little distorted and easy to identify on the chart.
  • Poor targets: a gently sloping tidal beach (the shoreline moves with the tide), gentle slopes (weak echo), buoys (blurred in waves, clear only close to).
  • Use the chart to judge a target: its spread, height and slope.
  • Caution: a nearer target can hide a larger one behind it. The radar picture is not a perfect plan view (see radar errors).
  • Minimum detection ranges required of a radar (clutter-free, antenna 15 m above sea level, IMO MSC.192(79); see radar performance standards):
    • shoreline rising to 60 m → 20 NM;
    • SOLAS ship over 5,000 GT → 11 NM; over 500 GT → 8 NM;
    • small vessel with radar reflector → X 5.0 / S 3.7 NM;
    • typical navigation buoy → X 4.6 / S 3.0 NM;
    • 10 m vessel with no reflector → X 3.4 / S 3.0 NM;
    • at short range, targets shown clearly from 50 m out to 1 NM (a buoy from 40 m) with only the range scale changed.
  • Real ranges change: a higher antenna sees further (but more sea clutter); super-refraction or sub-refraction changes the maximum range; rain hides targets much more on X-band than on S-band.
  • Do not plan to rely on radar alone: over-reliance on radar has caused collisions and groundings. Cross-check with other methods.

Record and approve

  • Record the plan: on the chart and in a passage plan form or notebook (waypoints, courses, distances, ETAs, UKC, calling points, contingencies).
  • The Master must approve it; the officers sign that they have read it.
  • Keep it on the bridge, available to every OOW.

The passage plan in ECDIS

In short: Depending on the ship’s certification, ECDIS may be the primary tool for passage planning. The same APEM rules apply, plus some ECDIS-only checks.

What to set up

  • Calculate the safety depth and safety contour and set them to the UKC required by the SMS.
  • Apply a maximum cross-track distance (XTD) to each leg, in line with the SMS and right for the area.
  • Check that ENCs are available for the whole passage, and use an appropriate large-scale ENC.
  • If you reuse an old route, check it again in full; remove old routes from the display.
  • Select the extra chart symbols / detail you need.
  • Set the ETA correctly, manually or with the route planning tools. A wrong ETA gives wrong tidal data and wrong time-dependent information.
  • Apply current and tidal data to the route, if integrated and up to date.
  • Then run the ECDIS route check for dangers along the XTD corridor.

Execution: ready to sail

In short: Execution starts when there is a time of departure. Fix the ETD/ETA, check the conditions, refine the plan, set the watches, brief the whole team, then carry out the plan (IMO A.893(21)).

Checks before departure

  • The ship’s navigational equipment: working and tested.
  • Tidal heights and streams at the critical points of the route (timing over shallow patches, narrows, bars).
  • Weather, including the chance of restricted visibility.
  • Passing dangerous points by day or by night: adjust the ETD if it matters.
  • Expected traffic conditions.
  • Then: detail the plan further where needed, refine the watch rotation, and brief everyone.

Master’s standing orders and night orders

The plan runs inside the Master’s orders (full detail in handing over the watch and calling the Master).

  • Standing orders: supplementary to the company’s standing orders, and specific to the vessel and the voyage. Typical examples:
    • respect all company standing orders; keep a proper look-out and safe speed at all times;
    • call the Master as the orders say, in any doubt, or in any emergency;
    • an extra look-out on the bridge from sunset to sunrise;
    • follow the COLREG at all times, including lights, shapes and sound signals;
    • radar must not be the only means of navigation;
    • monitor the weather every watch;
    • fix the position by methods other than GPS when available;
    • keep a radio watch on the right GMDSS equipment and frequencies;
    • call the Master if visibility falls below 3 NM, and put the engines on standby;
    • defer a change of watch that falls during a bridge operation until it is finished.
  • Night orders: supplementary to the standing orders, for the events expected that night. Typical examples:
    • follow the laid courses; fix and plot at the set intervals with primary and secondary methods;
    • call the Master at a set position or time; call if in any doubt;
    • anti-piracy watch; manning levels for each stage; engine room to stand by;
    • reduce speed at a set position, and the speed to keep;
    • prepare for arrival: call the Master, give the ETA to pilots and VTS, slow down about one hour before end of passage (as the engine needs), rig the pilot ladder in time, call the crew to stand by.

Monitoring: following the plan

In short: Once underway, watch the plan closely: deviation from track, progress and arrival times. The plan must be available at all times, and any change goes back through APEM (IMO A.893(21)).

What the OOW monitors

  • Progress against the plan: position, cross-track error, ETA at the next waypoint.
  • Position by more than one method: GNSS, radar ranges, visual bearings, soundings — never GPS alone.
  • Monitoring tools set up in the plan: parallel indexing and wheel-over — a parallel index line shows at once if the ship is off track, and the wheel-over point says exactly when to start each turn.
  • Bridge equipment: working, errors known.
  • Compliance with the COLREG, MARPOL, the standing orders, the GMDSS radio watch and the look-out (see OOW duties).

Calling the Master in the monitoring stage

  • At the calling points (position or time) written in the plan or night orders.
  • The seven-word list: Restricted visibility · Traffic · Gear failure · Crew sickness · Danger of navigation · Unsure · Emergencies.
  • Also when land, a mark or the expected soundings are not sighted on time, or appear unexpectedly.

Changing the plan, and the pilot

  • To change the plan underway: inform the Master, discuss the change and get the Master’s approval. The change itself goes through appraisal and planning again.
  • With a pilot on board, the Master stays responsible for the ship. When the Master is not on the bridge, the OOW acts for the Master. The pilot’s intentions are checked against our own plan.

⚡ Flashcards

Test yourself, one card at a time
  1. Q1Which rule makes a passage plan mandatory, and which IMO guidelines say how to make it?
    Answer

    SOLAS V/34; IMO A.893(21) Guidelines for Voyage Planning — APEM, berth to berth, all ships that go to sea.

    Common trap

    “Only for big ships”: small craft too, scaled to size, crew and voyage.

  2. Q2Can the OOW prepare the passage plan, or must it be the Master?
    Answer

    The OOW may prepare it; the Master must review and approve it, and the officers sign it.

  3. Q3What are the 5 Cs of seaworthiness checked in the appraisal?
    Answer

    Construction · Condition · Crew · Cargo · Compliance.

  4. Q4What publications would you consult during the appraisal stage?
    Answer

    Corrected charts and chart catalogue · Sailing Directions · Ocean Passages for the World and routeing charts · tide tables and tidal atlases · List of Lights · List of Radio Signals · weather information · Notices to Mariners (· NP100 for ice).

    Common trap

    Forgetting to check the corrections are up to date.

  5. Q5What do you mark on the chart in the planning stage?
    Answer

    Route and waypoints · no-go areas · UKC (with squat) and safe speed · TSS/VTS and reporting points · alteration and wheel-over points · fixing methods · Master-calling points · environmental areas. Then record it and get the Master’s approval.

  6. Q6Which targets would you choose for radar fixing in the plan, and which would you avoid?
    Answer

    Choose near, conspicuous, well-charted targets: capes, cliffs with headlands, isolated lighthouses or islands, jetties, racons. Avoid gentle tidal beaches, gentle slopes and buoys.

    Common trap

    A near target can hide a larger one behind it.

  7. Q7At what range must a radar detect a coastline rising to 60 m, and a ship over 5,000 GT?
    Answer

    20 NM and 11 NM (clutter-free, antenna 15 m — IMO MSC.192(79)). Over 500 GT: 8 NM.

    Common trap

    Rain cuts X-band range much more than S-band.

  8. Q8What must you set when planning on ECDIS?
    Answer

    Safety depth and safety contour from the SMS UKC · XTD for each leg · ENCs available, large scale · recheck any reused route · correct ETA (it drives the tidal data).

  9. Q9What do you check before departure in the execution stage?
    Answer

    Navigational equipment · tidal heights and streams at critical points · weather and visibility · day or night passing of dangers · traffic. Then ETD/ETA, watch rotation and a full team briefing.

  10. Q10What does the OOW do in the monitoring stage?
    Answer

    Keeps the plan available · checks progress, cross-track error and ETA · fixes by more than one method · uses parallel indexing and wheel-over · complies with COLREG, MARPOL, standing orders, GMDSS watch and look-out.

    Common trap

    Trusting GPS alone.

  11. Q11When would you call the Master during the monitoring stage?
    Answer

    At the planned calling points · Restricted visibility · Traffic · Gear failure · Crew sickness · Danger of navigation · Unsure · Emergencies.

  12. Q12You want to change the passage plan underway. And who is responsible with a pilot on board?
    Answer

    Inform the Master, discuss, get approval; the change goes through APEM again. With a pilot, the Master stays responsible (the OOW acts for the Master when the Master is not on the bridge).

📚 Resources

Video

Books

Regulations

  • MGN 610 (M+F) Amendment 1: SOLAS chapter V guidance — MCA, 2025 (Annex A 41: voyage planning, SOLAS V/34)
  • IMO A.893(21) Guidelines for Voyage Planning — the four APEM stages
  • SOLAS V/34 (safe navigation and avoidance of dangerous situations) and SOLAS V/34-1 (Master’s discretion)

Exam focus — MCA

Typical questions • “Explain the APEM system for passage planning.” → the four stages in order, each with two or three concrete actions; SOLAS V/34 and IMO A.893(21) named. • “You are Master: what would you consider in your appraisal for a voyage from Malta to Panama (or the Aegean to the Maldives)?” → 5 Cs, charts and publications, routeing charts and weather for the season, regulations and reporting systems, vessel readiness, crew. • “What publications would you consult during the appraisal stage?” → charts, Sailing Directions, Ocean Passages, routeing charts, tide tables/atlases, Lists of Lights and Radio Signals, Notices to Mariners. • “What do you consider when planning on ECDIS?” → safety contour/depth from UKC, XTD, ENC coverage and scale, rechecking old routes, correct ETA. • “When would you call the Master during the monitoring stage? Can you change the plan on your own?” → planned calling points plus the seven-word list; no — inform the Master and get approval. What examiners look for: the stages in the right order, berth to berth, real examples from your own voyages, the Master’s approval, and monitoring by more than one method.

Study material only: not legal advice and not a substitute for the official MCA, Transport Malta, IMO or flag-state texts.